An ordinance is undergoing a second reading to approve the detailed site plan for a new restroom addition at Brunswick Lake Park within the Brunswick Town Center Special Planning District No. 2. The project involves constructing a solid concrete facility with flushable toilets and will include new water and sewer connections, as well as electrical service, with the Medina County Park District funding the building and the City partnering on plumbing.
Commercial GCFoundations / footingsWater / sewer mainExcavation / gradingLandscaping / irrigationCommercial / industrial electrical
- What happened
- Brunswick City Council is reviewing an ordinance for the detailed site plan approval of a restroom addition at Brunswick Lake Park. This is the second reading of the ordinance.
- Why it matters
- The project requires construction of a new concrete restroom facility, which will involve general contracting, concrete work for foundations, and underground utility work for water and sewer connections. Site excavation, landscaping, electrical, and plumbing trades will also be needed.
- Timing
- The council is expected to hold a third reading. Following council approval, the facility will be ordered, which takes approximately one year for delivery, implying construction will follow after delivery.
Who to call
No contractor selected yet — the applicant/owner is the contact.