Headworks project construction ongoing — Water Reclamation Facility
Reviewed Oct 1 · outcome not yet confirmed
Every project links to the city packet it came from.
Construction for the Headworks Project at the Water Reclamation Facility is underway. Below-grade walls and floor slabs are complete, with above-grade walls and enclosure starting soon for electrical and mechanical installations.
Structural / formed concreteCommercial / industrial electricalCommercial plumbingCommercial HVACSteel erectionMisc / ornamental metals
- What happened
- The Headworks Project at the Water Reclamation Facility is actively under construction, with significant progress on structural elements and upcoming work on building enclosure and MEP systems.
- Why it matters
- The project is moving into the enclosure phase, which will involve electrical and mechanical contractors. Structural concrete work is largely complete, but specialized piping and electrical components are imminent.
- Timing
- The project is currently underway, with screens expected in October and mechanical/electrical work to follow enclosure of the structure.
Who to call
No contractor selected yet — the applicant/owner is the contact.
Named contact in the filing — locked
UnlockSource: canalwinchesterohio.gov
Related projects in Canal Winchester
- Water Reclamation Headworks Project progressing — Canal WinchesterSep 21
- Molto Building C building work underway — RobinettSep 21
- Canal Crossing mass grading underway — Rager and BixbySep 21
- Busey Road Park 10x10 shed plan moved to council — Busey RdSep 21
- Hill Road widening project funding commitment — Hill RdSep 21