Cincinnati, OH

Union Township EV Chargers Project proposed award — Union Township

Up for review Oct 13

Every project links to the city packet it came from.

Union Township awarded the design-build contract for the Union Township EV Chargers Project (PID #122828) to Donnellon McCarthy Enterprises in an amount not to exceed $947,540.00.

Budget: $948K

Solar / EV chargingCommercial / industrial electricalExcavation / gradingFlatwork (sidewalks, curbs, driveways)Low-voltage / data / security / AVStriping
What happened
The Board of Trustees selected Donnellon McCarthy Enterprises as the highest ranked design-build firm for the Union Township EV Chargers Project (PID #122828) under OKI Carbon Reduction Grant program funding.
Why it matters
Competitor intel: Donnellon McCarthy Enterprises has been awarded the design-build contract worth up to $947,540.00. Subcontracting opportunities for electrical, concrete flatwork, trenching, and site amenities may be available through the winning design-builder.
Timing
Contract award was approved on October 13, 2026, with final contract execution and design phase immediately following.

Who to call

No contractor selected yet — the applicant/owner is the contact.

Named contact in the filing — locked

Unlock

Source: utclermont.gov

Related projects in Cincinnati