Hilliard City Council authorized the City Manager to execute a contract with the Ohio Department of Transportation (ODOT) for the construction of the FRA-Cemetery Road SUP Project, approving an estimated expenditure of $3,145,570 plus a 10% contingency for bids exceeding estimate or change orders.
Budget: $3.1M
Paving / asphaltExcavation / gradingFlatwork (sidewalks, curbs, driveways)Water / sewer main
- What happened
- Hilliard City Council authorized a contract with the Ohio Department of Transportation for the FRA-Cemetery Road SUP Project with an estimated expenditure of $3,145,570.
- Why it matters
- Multi-use path and road improvements require site paving, excavation, concrete flatwork, and underground utility adjustments.
- Timing
- Bid due date is scheduled for November 12, 2026.