Lancaster, OH

South Water Plant force main valves engineering up for review

Reviewed Jul 13 · outcome not yet confirmed

Every project links to the city packet it came from.

The Service-Safety Director is authorized to enter into an engineering agreement for various construction administration services for the South Water Plant Force Main Backflow Valves Project. This resolution passed its third reading and was approved.

Water / sewer mainCommercial plumbingExcavation / grading
What happened
Lancaster City Council approved a resolution authorizing the Service-Safety Director to sign an engineering agreement for construction administration services for the South Water Plant Force Main Backflow Valves Project.
Why it matters
This agreement signals progress towards physical construction work involving force main valves at the South Water Plant. Trades involved will include utilities, plumbing, and associated excavation and site work.
Timing
The engineering agreement for construction administration means the project design is largely complete. Construction bid solicitations should be anticipated following this approval.

Who to call

No contractor selected yet — the applicant/owner is the contact.

Named contact in the filing — locked

Unlock

Source: lancasterohio.gov