The Certificate of Substantial Completion with Darby Creek Excavating, Inc. for Contract 1: Knollwood Wastewater Treatment Plant & Wintergreen Lift Station Consolidation was authorized for execution. Payment Application No. 10 for $188,574.97 for July 1-31, 2026, was also approved for the project.

Water / sewer mainExcavation / grading
What happened
The Certificate of Substantial Completion was executed and the tenth payment application approved for the Knollwood Wastewater Treatment Plant and Wintergreen Lift Station Consolidation project.
Why it matters
This indicates the project by Darby Creek Excavating, Inc. is nearing final completion, covering major underground utility and sitework components.
Timing
This project is substantially complete. Future work by this contractor or others on similar projects for the county would involve new bid opportunities.

Who to call

GC named — the winning contractor is the contact.

Named contact in the filing — locked

Unlock

Source: pickawaycountyohio.gov