Bennett Farm Fence Removal & Replacement Phase 1 awarded — Powell
GC named Oct 6 · sub buyout window
Every project links to the city packet it came from.
Ordinance 2026-22 authorizes the City Manager to award a bid to 76 Fence Columbus Northwest in the amount of $107,580.00 for Phase 1 of the Bennett Farm Fence Removal and Replacement Project.
Budget: $108K
FencingDemolition
- What happened
- Powell City Council introduced Ordinance 2026-22 to authorize the City Manager to award the fence removal and replacement contract to 76 Fence Columbus Northwest.
- Why it matters
- Serves as competitor intel for fencing and demolition contractors, as the Phase 1 project has been awarded for execution.
- Timing
- The public hearing and ordinance reading is scheduled for October 6, 2026, after which project mobilization is expected to proceed.
Who to call
GC named — the winning contractor is the contact.
Named contact in the filing — locked
UnlockSource: cityofpowell.us