Park improvements ongoing — JFK Park
Reviewed Jun 29 · outcome not yet confirmed
Every project links to the city packet it came from.
Improvements at JFK Park are ongoing, including concrete sidewalk installation, concession stand and restroom work, and curbing. The project is awaiting AEP electrical hookup with longer wiring and hopes for completion by the end of July.
Flatwork (sidewalks, curbs, driveways)Land clearing / tree serviceCommercial / industrial electrical
- What happened
- The Reynoldsburg Parks and Recreation Commission discussed ongoing improvements at JFK Park, noting progress on sidewalks, concession stand, and curbing, while awaiting electrical work.
- Why it matters
- The project is nearing completion but requires further electrical work (electrical.commercial) and general site work (sitework.clearing, concrete.flatwork). The ongoing nature indicates continued work on site infrastructure.
- Timing
- Completion is hoped for by the end of July, suggesting remaining work needs to be expedited.
Who to call
No contractor selected yet — the applicant/owner is the contact.
Named contact in the filing — locked
UnlockSource: reynoldsburg.gov