Ordinance No. 37-2026 authorizes a Community Reinvestment Area Agreement with D.D. Williamson Colors LLC to invest $59,200,000 to acquire and renovate an existing 129,515 sq ft building and install machinery for a food manufacturing operation. This project will create 87 new jobs.

Budget: $59.2M

Commercial GCSelective / interior demolitionCommercial HVACCommercial / industrial electricalCommercial plumbingDrywall
What happened
The City Council approved Ordinance No. 37-2026, authorizing a Community Reinvestment Area Agreement with D.D. Williamson Colors LLC. This agreement facilitates a $59.2 million project to renovate an existing building and install equipment for a food manufacturing operation.
Why it matters
This significant renovation project for a 129,515 sq ft industrial building will require extensive commercial general contracting, selective demolition, and significant mechanical, electrical, and plumbing work for the food manufacturing processes. Interior finishes and exterior envelope work are also implied.
Timing
The project is scheduled to begin no later than September 10, 2026, with all acquisition, construction, and installation to be completed by February 29, 2028.

Who to call

No contractor selected yet — the applicant/owner is the contact.

Named contact in the filing — locked

Unlock

Source: springdaleohio.gov