Johns Island Recreation Center GMP amendment up for review — Charleston

Reviewed Sep 22 · outcome not yet confirmed

Every project links to the city packet it came from.

Approval of Johns Island Recreation Center Guaranteed Maximum Price (GMP) Amendment #2 to the CMAR contract with Trident Construction LLC in the amount of $11,154,647.00 for an early release GMP package.

Budget: $11.2M

Commercial GCExcavation / gradingFoundations / footings
What happened
Council approved GMP Amendment #2 for $11,154,647.00 with Trident Construction LLC for early mobilization, delegated design, and procurement for the Johns Island Recreation Center.
Why it matters
Advances early-stage construction activities, material procurement, and site mobilization for the recreation center project under a CMAR delivery method.
Timing
Early release package execution begins immediately; final GMP and timeline to follow.