Lowline Early Site Package change order coming — Charleston
Reviewed Sep 22 · outcome not yet confirmed
Every project links to the city packet it came from.
Approval is sought for Lowline Revised Early Site Package Scope of Work Change Order #5 for $2,006,204.00 to facilitate a remobilization date of October 19, 2026. This change order must be approved by September 22, 2026.
Budget: $2.0M
Commercial GCExcavation / grading
- What happened
- A $2,006,204.00 change order for the Lowline Revised Early Site Package Scope of Work is on the agenda for approval to enable a remobilization by October 19, 2026.
- Why it matters
- This change order indicates ongoing or restarting site work for the Lowline project, suggesting general contracting and excavation needs. The remobilization date signifies active construction is imminent.
- Timing
- Approval on this agenda means site work will recommence on October 19, 2026, or soon thereafter.
Who to call
No contractor selected yet — the applicant/owner is the contact.
Named contact in the filing — locked
UnlockSource: charleston-sc.gov