Rec Center GMP Amendment up for review — Johns Island Recreation Center
Reviewed Sep 8 · outcome not yet confirmed
Every project links to the city packet it came from.
Approval of Guaranteed Maximum Price (GMP) Amendment #1 to the CMAR contract with Trident Construction LLC in the amount of $7,656,848.00 for an early release GMP package for timely mobilization, delegated design, and procurement of goods and supplies for the Johns Island Recreation Center project. This increases the CMAR contract to $7,731,848.00.
Budget: $7.7M
Commercial GCFlatwork (sidewalks, curbs, driveways)Commercial / industrial electricalRoofingFire sprinklerCommercial HVAC
- What happened
- The Committee approved a GMP amendment for the Johns Island Recreation Center project with Trident Construction LLC, providing funds for early mobilization, delegated design, and procurement.
- Why it matters
- This early release GMP signifies that the project is accelerating towards full construction, with initial phases (site prep, foundation, long-lead items) beginning soon. Subcontractor opportunities will be forthcoming through Trident Construction.
- Timing
- With an early release GMP package approved, construction activity is expected to commence soon, with bidding opportunities for subcontractors emerging rapidly.
Who to call
No contractor selected yet — the applicant/owner is the contact.
Named contact in the filing — locked
UnlockSource: charleston-sc.gov