Approval is sought for GMP Amendment #2, increasing the CMAR contract with Trident Construction LLC by $11,154,647.00 for the Johns Island Recreation Center project. This early release GMP package is for timely mobilization, delegated design, and procurement of goods and supplies.

Budget: $11.2M

Commercial GCExcavation / gradingFoundations / footingsSteel erection
What happened
An amendment to the CMAR contract with Trident Construction LLC for the Johns Island Recreation Center, increasing the GMP by $11,154,647.00 for an early release package, is on the agenda for approval.
Why it matters
This significant increase for an early release GMP indicates that major components of the recreation center are moving into procurement and construction phases, such as foundations, structural elements, and general site work. Trident Construction LLC will be soliciting bids from various trades.
Timing
Approval will allow for immediate mobilization, delegated design, and procurement, accelerating the project timeline.