The Landmarks Commission approved modifications to the front steps and railing at 79 N High Street, including removing sections of railing, replacing steps with pressure-treated cedar, and adding a new metal rail with specific conditions.

Commercial GCPainting / coatings
What happened
The Landmarks Commission approved modifications to the front porch steps and railing at 79 N High Street. This involves removing existing railing sections, replacing uneven and damaged steps with pressure-treated cedar, and installing a new metal rail with two legs and a top rail, but no spindles. Everything will be painted to match the current porch.
Why it matters
This project requires demolition of existing elements, carpentry for new steps, installation of metal railing, and painting of the new and existing porch elements. Power Washing will be needed post-construction clean-up.
Timing
The approval occurred on April 27, 2026. Construction can proceed after final permitting is secured.

Who to call

No contractor selected yet — the applicant/owner is the contact.