Canal Winchester, OH

Storm pipe replaced with box culvert — Robinett Way

Up for review Oct 12

Every project links to the city packet it came from.

A variance is requested to replace an existing 48-inch storm pipe with a new 24-foot by 5-foot box culvert. This is to accommodate a new access drive for a previously approved 210,748 sq. ft. speculative industrial building.

Excavation / gradingStorm drainagePrecast / prestressedHauling / truckingPaving / asphaltCommercial GC
What happened
The Planning and Zoning Commission is reviewing a variance request (VA-26-018) for a property at 7750 Robinett Way. The request is to replace an existing 48-inch storm pipe with a new 24-foot by 5-foot box culvert.
Why it matters
This project involves significant earthwork, excavation, and storm infrastructure installation, specifically a large box culvert. It is related to the development of a large industrial building, meaning sitework and utility contractors will be needed.
Timing
This is an agenda item for review, so a decision on the variance is pending. If approved, detailed design and permitting will follow.

Who to call

No contractor selected yet — the applicant/owner is the contact.

Named contact in the filing — locked

Unlock

Source: canalwinchesterohio.gov