Street program underway — Canal Winchester
Reviewed Jun 1 · outcome not yet confirmed
Every project links to the city packet it came from.
The street program is active, with miscellaneous curb repairs completed and restoration work beginning this week. The sidewalk program is also active, with panel replacements and restoration starting.
Paving / asphaltFlatwork (sidewalks, curbs, driveways)Excavation / gradingPower washing / pressure cleaning
- What happened
- Council received an update on the ongoing street and sidewalk programs, indicating completion of curb repairs and commencement of restoration work.
- Why it matters
- The street program includes concrete repairs (curbs) and general restoration. The sidewalk program involves concrete panel replacement and restoration. Power washing may be required for surface cleaning prior to or during restoration.
- Timing
- Restoration work for both programs is beginning the week of May 18, 2026. This is an active construction phase.
Who to call
No contractor selected yet — the applicant/owner is the contact.
Named contact in the filing — locked