Cuyahoga Falls, OH

20 MW AC solar array EPC replacement approved — Hardy Road Landfill

Approved Oct 26 · confirmed in minutes

Every project links to the city packet it came from.

Temp. Ord. A-91 authorizes Advanced Solar Products, Inc. to replace CS Energy as the engineering, procurement, and construction (EPC) partner to CEP Renewables, LLC for the 20 MW AC solar array located at the Hardy Road Landfill.

Solar / EV chargingCommercial / industrial electricalCommercial GCUnderground electrical / telecom
What happened
Council introduced legislation approving Advanced Solar Products, Inc. as the new EPC contractor for the 20 MW AC solar array project at the Hardy Road Landfill, including performance and payment bonding requirements.
Why it matters
The change in EPC contractor triggers subcontracting and supply chain opportunities for electrical, solar installation, and site civil trades supporting the 20 MW solar array build.
Timing
The ordinance was introduced on October 26, 2026, as an emergency measure to formally transition the EPC contract and bonding.