Cuyahoga Falls, OH

20 MW solar array EPC partner replacement — Hardy Road Landfill

Up for review Nov 2

Every project links to the city packet it came from.

Temp. Ord. A-91 authorizes Advanced Solar Products, Inc. to replace CS Energy as the engineering, procurement, and construction (EPC) partner for the 20 MW AC solar array at the Hardy Road Landfill, including performance and payment bonding.

Commercial / industrial electricalSolar / EV chargingExcavation / gradingErosion & sediment control
What happened
City council scheduled discussion on Temp. Ord. A-91 to approve Advanced Solar Products, Inc. as the new EPC contractor for the 20 MW solar array project.
Why it matters
The EPC replacement involves electrical and solar installation work, requiring electrical contractors and site preparation trades.
Timing
Legislative review on November 2, 2026, followed by formal council action.

Who to call

No contractor selected yet — the applicant/owner is the contact.

Named contact in the filing — locked

Unlock

Source: cityofcf.com

Related projects in Cuyahoga Falls