Lawrence Street pump station replacement up for review — Lancaster
Reviewed Oct 12 · outcome not yet confirmed
Every project links to the city packet it came from.
City Council passed Resolution Temporary 88-26 authorizing a construction contract for the Lawrence Street Pump Station Replacement Project.
Water / sewer mainCommercial / industrial electricalFoundations / footingsCommercial HVAC
- What happened
- City Council approved Resolution Temporary 88-26 for the construction of the Lawrence Street Pump Station Replacement Project.
- Why it matters
- Pump station replacement requires heavy utility work, structural concrete foundations, electrical controls, and mechanical equipment installation.
- Timing
- Contract authorization is complete, and construction initiation follows immediately.
Who to call
No contractor selected yet — the applicant/owner is the contact.
Named contact in the filing — locked
UnlockSource: lancasterohio.gov
Related projects in Lancaster
- Tiki Lane waterline replacement project up for review — LancasterOct 12
- South Water Plant backflow valves project up for review — LancasterOct 12
- Columbus St & Wilson Ave sewer separation out to bid — LancasterOct 12
- Final Plat for Section 3 of the Overlook Development — LancasterOct 26
- Final Plat for the Timber Run Development — LancasterOct 26