Living-quarters footers are poured and the pond completed for the new Fire Station 122 build, with CMU work expected by month-end and apparatus bays to follow. Hydrovac excavation around high-pressure gas lines is scheduled.

Block / CMUExcavation / gradingGas lineErosion & sediment controlTraffic control / flagging
What happened
The Plain Township Board of Trustees reviewed ongoing construction progress for Fire Station 122, noting poured footers, completed pond work, and upcoming hydrovac excavation around high-pressure gas lines.
Why it matters
Progress on foundations and upcoming masonry work indicate active structural scopes, while utility excavation requires specialized coordination.
Timing
CMU block work is expected by month-end, with apparatus bays following and an anticipated completion in mid-2027.

Who to call

No contractor selected yet — the applicant/owner is the contact.